Friday, 30 April 2010

New driveway created & first signs of construction

New driveway created




Soak aways created


First signs of construction! Steel put in place.



Thursday, 29 April 2010

Trees cleared


Goodbye leylandii

Front door gone!


Fireplace removed


Wednesday, 28 April 2010

Floors go and trenches dug


Trenches for drains are dug

Trench for water main dug

Floors removed

Friday, 23 April 2010

Staircase goes!

Utility Wall demolished

Backdoor removed



Trench dug for new wall between Kitchen and study and downstairs wc


Cesspit filled

Staircase removed


Room with a view!


Thursday, 22 April 2010

More demolition


More windows are removed


Old pond removed


The builders begin to fill in old cesspit


Kitchen and annexe floor dug up



Monday, 19 April 2010

Thursday, 15 April 2010

Tuesday, 13 April 2010

Monday, 12 April 2010

Friday, 9 April 2010

Roof removed

    
  

Thursday, 8 April 2010

Wednesday, 7 April 2010

Tuesday, 6 April 2010


The builders remove the good tiles and broken ones are skipped. Although we are replacing the tiles the old ones will be sold.


Monday, 5 April 2010